Week 25: Paint Continues

Image
Trim and doors are now done... next were the ceilings.  Once those were done, Kevin came by and installed all of the pot lights in the house.  Looking good!

Week 24: Trim and Doors Installed

Image
Trim and doors are now complete and Mick has made good progress on painting.  The trim and doors should be painted by early next week.

Week 23: Basement Floors and Outside Touches

Image
Mick has covered all of the floors and Jampa has started installing the window trim, door frames and baseboards.  By week's end, he was just starting the floors. Meanwhile, the outside is getting to a state where we can start landscaping soon.  Caulking was done, garage door installed and the porch ceiling was finished with some prefinished faux-wood look vinyl.  Jampa got so ahead that he was able to start the vinyl floors in the basement.

Week 22: Flooring Complete

Image
Jampa started on the beautiful prefinished floors (sorry, no pic!) and Fred put the finishing touches on the wall tile in the three bathrooms that have tile.