Posts

Showing posts from March, 2018

Week 3: Framed front, walls topped up

Image
In our third week, we took advantage of some nice weather and got the front and some of the main floor walls framed up.  Tom was also able to pour the extra height on the existing walls (bringing interior ceilings up to ten feet) and start the rear addition foundation.

Week 2: Excavation and footings

Image
After removing a whopping 17 bins of garbage and clean fill, we have a clean project to start working from.  Thom has the addition dug out and has poured his footings.  If all goes well with the weather, we'll complete the foundation next week.

Week 1: Demolition begins

Image
Demolition begins this week.  Unfortunately, due to the nature of the project, this will largely be a "by hand" demolition job.  In a week or so, we should be ready to dig the addition out back.  Stay tuned...

New project launch

Image
Welcome to 40 Cardigan Road!  Demo begins shortly....