Week 11: Pluming, electrical and... kitchen arrives??

Plumbing didn't take long to rough in - Tony and Mario were done in about 3 days, and we'd had the system inspected and passed by Thursday.  Also passed were the framing and HVAC inspections, we we are pushing towards the insulation phase.... we just need the windows !?!?! :-).





For clarity sake, I painted the kitchen layout on the floor to give everyone an idea of the layout and to help the three main rough-in trades (HVAC, plumbing and electrical) get a feel for where things are going.  It seems like a really great size for the space.


Lastly, the open riser basement stairs arrived - they will look great when revealed!